The view down the Phase 2/3 Maintenance Corridor with redundant electrical rooms on either side
Even with the rainy weather, the installation of the precast walls is quickly progressing. Incredibly, where just a week ago there was open ground, you can now walk around the Phase 2 and 3 north data rooms. Admittedly they are a bit bare as of now, but it is easy to start imagining what the finished product will look like.


Being able to make last minute tweaks to everything from cable tray placement to the color of the ceiling tiles has proven invaluable to the design team. By reviewing the design before the first build-out, we've been able to make sure that we'll have the best design possible for future tenants.

Looking into the entrance to Phase 2 from a Data Room

Future Loading Dock and Staging Area
Being able to make last minute tweaks to everything from cable tray placement to the color of the ceiling tiles has proven invaluable to the design team. By reviewing the design before the first build-out, we've been able to make sure that we'll have the best design possible for future tenants.

Pouring concrete
(Click on Read More to view more photos)
Week 11 Construction Gallery
(Ed. Note: Check back weekly every Tuesday for a new photo gallery of the past week's construction process)
Previous Weeks:
Week 10 (Data Room Mock-Up)
Week 9 (Precast Walls)
Week 7/8 (Backfilling Underground)
Week 6 (Electrical Underground Completion)
Week 5 (Electrical Room Underground)
Week 4 (Foundation and Underground)
Week 3 (Foundation and Snow)
Week 2 (Foundation)
Week 1 (Excavation)
Pre-Construction
Previous Weeks:
Week 10 (Data Room Mock-Up)
Week 9 (Precast Walls)
Week 7/8 (Backfilling Underground)
Week 6 (Electrical Underground Completion)
Week 5 (Electrical Room Underground)
Week 4 (Foundation and Underground)
Week 3 (Foundation and Snow)
Week 2 (Foundation)
Week 1 (Excavation)
Pre-Construction