Recently a major milestone was completed with the delivery and installation of the modular Epsilon Industries Chiller Plant Building. Weighing in at over 250,000 lbs and completely pre-built in Ontario, Canada, the building was delivered and installed over the course of two very exciting days. Designed to take advantage of Free Cooling, the building will allow TEAM to stay very energy efficient while supporting the overall data center expansion.

QUICK FACTS
  • Customized, Pre-Engineered, Assembled, and tested in factory controlled environment
  • Shipped from Kingston, Ontario Canada
  • Total Operational Weight: 250,000 lb
  • Alerton Chiller Plant Controls Designed to TEAM standards for Uptime and Concurrent Maintainability
  • McQuay 550 Ton Premium Efficiency Centrifugal Chiller with VFD, manufactured in Staunton, VA
  • Evapco Cooling Towers utilizing ultra quiet package composed of low noise fans and water silencers, manufactured in Taneytown, MD
  • Integrated Free Cooling to take advantage of colder Northern Climate, thus decreasing Data Center PUE
  • Set by crane in two days
  • Building composed of 4 sections: Indoor chiller building section, pre-piped mezzanine section, Evapco Towers, Screen wall
  • All piping hung from ceiling to maximize maintenance personnel space
  • Cooling Towers placed on top of mezzanine section and fully supported by building